VTrans Project # TAP TA23(8)

Completed Tasks

  • December 2022 – Submitted Grant Application
  • March 2023 – TAP Selection Committee awarded $48,000 in funding for Village Scoping Study project with a required local match of $12,000.
  • June 2023 – Selectboard hires Rita Seto of TRORC as the Municipal Project Manager (MPM). At-the-Ready Consultant Selection process results in contract negotiations with Fuss & O’Neill
  • September 2023 – Contract with Fuss & O’Neill fully executed. Scoping study is officially underway
  • October 2023 – Scoping Kick Off meeting with MPM, Town, VTrans Municipal Assistance and Fuss and O’Neill
  • November 2023 – Local Concerns Meeting hosted by the Selectboard at the Sharon Elementary School
  • October 2024 – Alternatives Presentation Meeting hosted by the Selectboard at Steele Chapel

Helpful Documents

Fuss & O’Neill Local Concerns Presentation

VTrans State Highway Right of Way Pamphlet

Purpose & Needs Statement

Local Concerns Meeting Notes – Final

Fuss & O’Neill Alternatives Presentation